I’m sure everyone is wondering why the big pile of rocks at
the Learning Center has been sitting there for a few months and why there is equipment
and missing bunkers dotted over a few holes.
The edge of the irrigation pond had been eroding over the
last couple of years to the point where it needed reinforcing. While
researching the best option, we were able to source some huge boulders locally,
which will provide the best aesthetic solution to reinforce the banks. The plan
was to excavate the old edge, build a shelf to place the boulders on, and then
backfill behind them. Once the shelf was built (and the weather cooperated) we
contacted the pond liner contractor to install the liner, only to find out it
had been backordered. We had anticipated a delay so ordered it last fall to
make sure it was here, however, as with it seems everything this year, we are
at the mercy of the shipping companies. It is now supposed to be installed by mid-April,
so hopefully this is the last delay. The rest of the project should only take a
couple of weeks to complete once the liner is in place.
|
The old pond liner and erosion on 14 pond |
|
Unloading the boulders |
As you know, the board approved the greenside bunkers to be
replaced this spring. The recommended life of bunker and is approximately seven
years, so the 17-year-old sand at LedgeRock is well past its sell by date. The rebuilt
bunkers will be constructed using the best method/materials available; this
will ensure that the money spent now will pay off in the long term as it
virtually reduces all contamination of the sand, ensuring that the new bunkers
will greatly exceed the current recommended life span. We have sourced an
excellent bunker sand to complement the project.
|
Bunker washouts from 6+" of rain from Hurricane Ida Sept 2021 |
|
Bunker washouts from 6+" of rain from Hurricane Ida Sept 2021 |
|
Slight bunker washout on new bunker on 17 from Hurricane Ida showing how well the liners work preventing washouts while keeping the sand clean even after more than 6" of rain |
|
New fairway bunker on 12 showing the liner (Blinder) and edge structure (EcoBunker) |
Now that the course is approaching its third decade, the club
contacted Rees Jones so, as part of the reconstruction, they can make any changes
needed to ensure the design continues to challenge into the future. The added
benefit of this is that we can reduce the sand area, which will save money on maintenance
in the future. It is amazing how architects can reduce sand area but without affecting
the visuals and playability, so I cannot wait to see the finished product.
|
Alan, Asst Super Cody, Bryce Swanson (Rees Jones Inc) & Brian Ley (contractor) checking out 16 |
A perfect example of what we are doing, is on 18. The left
bunker is getting tweaked to fit into the land better but also the front edge
is getting lowered so there will be more sand visible from the fairway – one of
the architect tricks to make it look bigger, when it will actually be smaller.
The front bunker gets broken into two, with the smaller part nearer the approach
being raised so you can now see the greens surface from it, while the other
part remains similar to the old version. They are also lowering the front edge
so there will be more sand visible from the fairway, making it aesthetically
better and more visually intimidating, while also making it a little easier!
|
Quick sketch from Rees Jones showing the changes on 18 |
|
New bunkers shaped on 15 |
The plan was to start in early April and have the project completed
by June 1st. The contractor was able to get a head start on the
project with a couple of staff and hence why it currently looks to be moving
slowly. He is still on schedule to have a full crew here as planned in April
and the progress will move quickly from then on.
Over the next week the bunker sand will start to be delivered
and stockpiled in the parking lot. Once the contractor gets fully started in April,
we plan to send out regular updates on the progress. It has been a frustrating start
due to the delays with materials - however I am glad we got a head start so did
not run into these issues later which would have greatly delayed the original
schedule. So sorry about the mess but bear with us for the next couple of
months as it will not be long until it is all put back together and LedgeRock
will look and play better than it ever has!
As always, please email me with any questions: alan@ledgerockgolf.com